Delhi Metro completes Kashmere Gate-Red Fort tunnel

New Delhi, Aug 3 (IANS) The Delhi Metro on Monday completed the 1,351 metre tunnelling between Kashmere Gate and Red Fort.

Constructed under the Delhi Metro Rail Corporation’s (DMRC) Phase – 3, the stretch of tunnel on the 9.37 km long Central Secretariat – Kashmere Gate corridor passed beneath the existing Kashmere Gate elevated metro station.

“The tunnel boring machine emerged at (Red Fort) Lal Qila metro station site after making a 1,351 metre-long tunnel from Kashmere Gate. The initial drive of the tunnel which is 16 metres below the surface began on December 26, 2014,” the DMRC said.

“The tunnel passed under the historical Dara Shikoh Library, Lothian Bridge (Delhi – Shahdara Northern Railway Line), and Ambedkar University,” it added.

Leave a Reply

Please enter your comment!

The opinions, views, and thoughts expressed by the readers and those providing comments are theirs alone and do not reflect the opinions of www.mangalorean.com or any employee thereof. www.mangalorean.com is not responsible for the accuracy of any of the information supplied by the readers. Responsibility for the content of comments belongs to the commenter alone.  

We request the readers to refrain from posting defamatory, inflammatory comments and not indulge in personal attacks. However, it is obligatory on the part of www.mangalorean.com to provide the IP address and other details of senders of such comments to the concerned authorities upon their request.

Hence we request all our readers to help us to delete comments that do not follow these guidelines by informing us at  info@mangalorean.com. Lets work together to keep the comments clean and worthful, thereby make a difference in the community.

Please enter your name here