Govt allows Force Majeure, grants up to 4-month relief to contractors amid West Asia crisis

Spread the love

Govt allows Force Majeure, grants up to 4-month relief to contractors amid West Asia crisis

New Delhi: In a bid to provide relief to contractors amid the fast-evolving West Asia situation, the government has allowed them to invoke ‘Force Majeure’ in view of disruptions, recognising “war” as a valid trigger under procurement rules.

In an office memorandum, the Ministry of Finance said the prevailing conditions in West Asia should be treated as a war-like event for contractual purposes, enabling relief to contractors impacted by delays.

Under the revised guidance, contracts with completion deadlines on or after February 28, 2026, that have been affected directly or indirectly by the West Asia disruptions may be granted an extension of at least two months and up to four months, without any penalty or additional cost to contractors.

“Not with standing the punitive provisions contained in the contract for delay or breach of contract, the supplier would not be liable for imposition of any such sanction so long as the delay… is the result of an event covered in the FM clause,” the memorandum noted.

Moreover, the government also reiterated that delays attributable to ‘Force Majeure’ must be assessed on a case-by-case basis, with procuring entities required to re-fix delivery or completion timelines without imposing liquidated damages or denial clauses.

However, the relief comes with conditions.

Invocation of Force Majeure will be considered valid only if contractors were not already in default as of February 27, 2026, and only for disruptions directly linked to the West Asia situation.

Contracts may still be terminated by either party if Force Majeure conditions persist beyond 90 days, without any financial repercussions.

“All contractual obligations shall revive upon completion of the period,” the ministry added.

The clarification builds on provisions outlined in the “Manual for Procurement of Goods, 2024”, “Manual for Procurement of Consultancy Services, 2025”, “Manual for Procurement of Non-Consultancy Services, 2025” and “Manual for Procurement of Works, 2025”, which define Force Majeure as extraordinary events beyond human control, including war, strikes, riots and natural calamities.

 


Spread the love
Subscribe
Notify of

The opinions, views, and thoughts expressed by the readers and those providing comments are theirs alone and do not reflect the opinions of www.mangalorean.com or any employee thereof. www.mangalorean.com is not responsible for the accuracy of any of the information supplied by the readers. Responsibility for the content of comments belongs to the commenter alone.  

We request the readers to refrain from posting defamatory, inflammatory comments and not indulge in personal attacks. However, it is obligatory on the part of www.mangalorean.com to provide the IP address and other details of senders of such comments to the concerned authorities upon their request.

Hence we request all our readers to help us to delete comments that do not follow these guidelines by informing us at  info@mangalorean.com. Lets work together to keep the comments clean and worthful, thereby make a difference in the community.

The opinions, views, and thoughts expressed by the readers and those providing comments are theirs alone and do not reflect the opinions of www.mangalorean.com or any employee thereof. www.mangalorean.com is not responsible for the accuracy of any of the information supplied by the readers. Responsibility for the content of comments belongs to the commenter alone.  

We request the readers to refrain from posting defamatory, inflammatory comments and not indulge in personal attacks. However, it is obligatory on the part of www.mangalorean.com to provide the IP address and other details of senders of such comments to the concerned authorities upon their request.

Hence we request all our readers to help us to delete comments that do not follow these guidelines by informing us at  info@mangalorean.com. Lets work together to keep the comments clean and worthful, thereby make a difference in the community.

0 Comments
Inline Feedbacks
View all comments
wpDiscuz
0
0
Would love your thoughts, please comment.x
()
x
Exit mobile version